Glendale
Client: EPTCON
Station design of 44kV substation including equipment layout, substation bill of materials, site grading, foundation design, pole framing, plan and profile, and design of steel support structures
Year: 2012
Ashfield HONI 500kV station
Client: EPTCON
Preparation of fabrication drawings of structural steelwork for 500kV HONI Switch Yard
Year: 2013
NextERA: Parkhill
Client: One Line Engineering
Station engineering and detailing for tender and construction of new 525kV / 121kV switching station. Scope included engineering of station layout and bill of materials, design of rigid bus to interface with existing Hydro One Station, direct lightning stroke protection, spill containment, and civil & structural engineering.
Year: 2012 - Current